Follow Us


Neighborhood Streetscape Improvements

January 15, 2020

EAST AREA IMPROVEMENTS (EAST NEIGHBORHOOD BETWEEN PONCE DE LEON AND DOUGLAS):

The design and permitting process for all elements east of Ponce has been completed. After a long and tedious process, the Civil drawings that were submitted to the Miami Dade county traffic engineering department last year have been finally approved. We have finalized and signed the design-build contract with Superior Landscaping Inc., for the East area improvements and Superior Landscaping is now submitting the completed drawings and documents to the City of Coral Gables for a permit.  Construction can finally start.

Now that the design is finalized and with the contractor on-board, the schedule for the improvements is as follows:

• AREA #1 – East side – permit issuance by City – May 2020, Construction start in June 2020 and to be completed by December 2020
• AREA #2 – South Side  (Santander+ San Sebastian East of Ponce)- Construction start in December 2020, to be completed by May 2021

We are excited to finally be able to start the neighborhood streetscape upgrades in the area and remain committed to getting this project completed within the projected schedule.

WEST AREA IMPROVEMENTS (CATALONIA AV, MALAGA AV., AND SANTANDER AV.) BY LEJEUNE:

The West area remains on-hold as we await the final direction from The City of Coral Gables (that may come after further meetings with the area neighbors).

 

 

Note: All questions pertaining to the scope of this project should be directed to the CITY OF CORAL GABLES, PUBLIC WORKS DEPARTMENT.